Projmors has become an advisor in the process of obtaining permits for the MFW Bałtyk II and MFW Bałtyk III projects

The companies implementing the MFW Bałtyk II and the MFW Bałtyk III projects have signed a contract with Biuro Projektów Budownictwa Morskiego Projmors. Thus, the company from Gdańsk has become an advisor in support of obtaining the Building Permit for both projects.

The contract includes, among others, preparation of the building design for the MFW Bałtyk II and MFW Bałtyk III and the power output infrastructure, advice on the required expertise and obtaining all required Building Permits. According to the schedule, work related to obtaining the necessary permits is to be carried out by the end of 2023.

After obtaining the required permits, concluding the necessary agreements and provided that the final investment decision is made by Polenergia and Equinor, the construction works related to the construction of the MFW Bałtyk II and MFW Bałtyk III could start at the turn of 2023 and 2024.